Concrete piles were being placed and driven in the construction of a new bridge with a barge-mounted crane. The first 55-foot section of the concrete pile had been driven, and the second 110-foot concrete section of the pile had been set in place and secured to the first concrete section of the pile.

 The pile driving leads were adjusted and the hammer was positioned on top of the second concrete section of the pile in preparation to drive the pile. The concrete pile broke and started collapsing. As the pile collapsed and fell, the leads were pushed to the right of the crane boom. This caused severe side loading to the crane and the entire crane was flipped onto its right side.

 The falling concrete pile and falling portions of the crane crushed and killed one employee, the crane operator. Another worker at the site was injured by falling objects and was hospitalized for treatment of fractures.

Current Issue

Current Issue of Marine Construction Magazine

Advertisement

Additional Stories

Permits issued for Chicago’s Navy Pier Marina, construction set to begin this year

Permits issued for Chicago’s Navy Pier Marina, construction set to begin this year

Transient marina project has received all permits to commence construction for a

Hoisting – A Guide to Doing It Safely  

Hoisting – A Guide to Doing It Safely  

Hoisting material is a critical part of all marine construction, from pile

Eastern Shipbuilding Group Building Hopper Dredge for USACE

Eastern Shipbuilding Group Building Hopper Dredge for USACE

Eastern Shipbuilding Group, Inc. (ESG) has officially begun construction on the U.S.

FUEL DISPENSING AREAS

FUEL DISPENSING AREAS

The fuel dispensing area should be located a sufficient distance from other