The Magazine of the
Marine Construction Industry

Casper, Phillips & Associates Remedies Gearbox  Failure after Root Cause Analysis at Port   

Reading Time: 3 Minutes

952 Views

All three 40-metric ton capacity cranes span 54.75 meters over four rail tracks and three truck lanes.

Casper, Phillips & Associates, Inc. (CPA) recently completed remediation of three 40 metric-ton capacity rail-mounted gantry cranes (RMGs) at a  major North American port, after conducting a  root-cause analysis following gearbox failure.   

CPA offers a wide variety of services, including procurement, specification, design, manufacturing review, modification, and accident investigation.  The company was contracted by the port, as the  RMGs’ main hoist gearbox bearings and gear teeth were experiencing early failure and excessive vibrations. CPA was retained to investigate the causes and to provide retrofit solutions.  Gearboxes fail for several reasons, such as soft foundations,  misalignment, overload, poor contact,  and sometimes poor design practices.   

Mike Zhang and Richard Phillips, both mechanical engineers at CPA, completed the initial site investigation on an RMG that was used for intermodal  (moving freight by two or more modes of transportation)  container handling. It was apparent that under load the drum would bend the gearbox output shaft. The bending of the shaft caused the gear teeth to misalign. In other words, only parts of the gear teeth were in contact, which led to rapid wear. 

Expert ear   

Phillips said, “Since all three cranes had the same issue, the port picked the crane that minimised interruptions to yard operations. They did not have to close the port—just the area where this crane operated while we were observing the issue.   

“After we determined it was safe, we had the port demonstrate the issue. We went up on the crane and an operator used the hoist. Mike listened to the gearboxes and observed the noise during hoisting.  The issue became obvious once we noticed the hoist drivetrain did not have a coupling between the gearbox output shaft and the drum. To keep the  cranes in operation unit repairs could be made, the  port reduced the crane hoist speed by 50%, which  reduced productivity by half.”   

Original equipment—the drum is directly mounted to the gearbox output shaft.

All three cranes, which move containers on and off ships, trains, and trucks, can pick up single 20-foot  or 40-foot containers. They span 54.75 meters over four rail tracks and three truck lanes. Lift height is 40 feet, which is good for lifting one container over a stack of three containers high. The approx.  gearbox dimensions, meanwhile, were 0.58 meters wide, 2.1 meters long and 0.94 meters tall. The drum has a 0.985-meter pitch diameter and is 3.1  meters long.   

New hoist system   

CPA first redesigned the hoist system to use a drum coupling that allows misalignment between the gearbox output shaft when the drum is loaded. This allows the output shaft of the gearbox to stay in alignment under all drum loads, which means the gear mesh will stay in alignment too. The replacement parts were fitted in the same space as the original components, and the strength and stiffness of the gearbox foundation were increased to meet operational requirements.   

CPA also helped port representatives to source new powertrain components, including gearboxes,  drum couplings, and the hoist drum. Zhang added:  “While the components were under order, I took the client over to visit the shop that was producing the powertrain components. We hired a third-party inspection company to perform quality assurance and quality control inspections. After the components  were delivered, Richard [Phillips] and I assisted the  port with installation and commissioning.”   

New equipment including drum coupling being installed and aligned.

CPA’s eventual scope of work would include assisting the port in all new component fabrications;  quality assurance (QA) and quality control  (QC) audits; installation assistance; and acceptance.   

The entire project from design to acceptance tests for all three RMGs was completed within six months. The end customer was pleased with the performance of the new hoist systems and CPA’s expert services.   

This type of machinery failure investigation and repair is not common for CPA; in fact, this kind of project amounts to only 10% of the company’s workload. As Phillips explained, these are the type of issues it prevents by performing a design review before the cranes are built. 

Current Issue

Current Issue of Marine Construction Magazine

Advertisement

Additional Stories

Crane Fatigue – The Devil is in the Detailing Connection detailing is an underrated art form, especially on cranes.

Crane Fatigue – The Devil is in the Detailing Connection detailing is an underrated art form, especially on cranes.

By Richard Phillips In the crane design world, how beams are joined

OZ Lifting Launches Stainless Steel Chain Hoist 

OZ Lifting Launches Stainless Steel Chain Hoist 

OZ Lifting Products LLC has launched the first in a new range

Garco operates Link-Belt cranes 24/7 on Seattle Convention Center project

Garco operates Link-Belt cranes 24/7 on Seattle Convention Center project

In the second quarter of 2019, the Seattle, Washington City Council reached

Liebherr mobile harbor crane celebrates 50th anniversary

Liebherr mobile harbor crane celebrates 50th anniversary

The LGM 1130 introduced in 1974 was Liebherr’s first mobile harbor crane,