Marine Construction® Magazine

  • Home
  • RESOURCES
    • EQUIPMENT
    • MATERIALS
    • MANUALS
    • SERVICES
    • LEGAL
    • EDUCATION
    • SAFETY
  • SUBSCRIPTION
    • PREVIOUS ISSUES
  • SOFTWARE
  • ADVERTISING
  • WEBINAR
  • VIDEOS
  • CONTACT
  • BLOG
  • Classifieds
  • Jobs
MCMag NEWS
  • Link-Belt HTC-86100 Builds Cruise Terminal at Port Canaveral, Fla.   |   Jul 25 2022

  • Aarsleff’s Centrum Pile System does double duty on Dutch photovoltaic project   |   Jul 24 2022

  • Port of Los Angeles Enters Agreement with IBM to Create Cyber Resilience Center      |   Jul 17 2022

  • Greek temple ruins suggest cranes were in use as early as 700 B.C.   |   Jul 15 2022

  • Smith Brothers builds in Chesapeake Bay for more than 100 years   |   Jul 15 2022

  • Buried Wharves Uncovered on Manhattan Waterfront   |   Jul 15 2022

 
You are at :Home»EQUIPMENT»FLOATING PILE DRIVING RIGS

FLOATING PILE DRIVING RIGS

MCMag Mar 26 2019 EQUIPMENT, MATERIALS Comments Off on FLOATING PILE DRIVING RIGS 4287 Views

When pile drivers are working over water, all relevant precautions for work over water should be taken in
accordance with this code and in particular a suitable boat should be kept readily available at all times.
More specifically…

  • All members of floating pile driving crews should be trained to handle boats.
  • Floating pile driving rigs should be provided with a whistle, siren, horn or other effective signaling equipment.
  • Floating pile driving rigs should be provided with adequate fire-fighting equipment.
  • The weight of machinery on a floating pile driving rig should be evenly distributed so that the deck of the installation is horizontal.
  • Steel barge hulls should be divided into watertight
    compartments.
  • Watertight compartments should be provided with siphons
    for the removal of water seepage.
  • Barge deck hatches should have firmly fastened covers that
    fit flush with the deck.
  • Sufficient sheaves should be provided on the barge deck to
    enable the crane or pile driving rig to be safely maneuvered
    in any direction and safely secured in position.
  • Regular headcounts should be taken of the pile driving
    crewmembers.

During lifting operations, the stability of the floating crane/
derrick or vessel with an auxiliary shipboard crane shall meet
the USCG requirements for “Lifting”.
The load rating of a floating crane/derrick shall be the
maximum working loads at various radii as determined by the
manufacturer or qualified person considering list and trim for
each installation. The load rating shall specifically reflect the:
design standard; machine trim; machine list; and dynamic/
environmental loadings anticipated for the operational
envelope of the floating crane/derrick or auxiliary shipboard
crane.
The load rating is dependent upon the structural competence
of the crane or derrick, rope strength, hoist capacity, structural
attachment to the floating platform, and stability and freeboard
of the floating platform.
When deck loads are to be carried while lifting, the situation
shall be analyzed for modified ratings.
When mounted on barges or pontoons, the rated loads
and radii of land cranes and derricks shall be modified as
recommended by the manufacturer or qualified person. The
modification should always be evaluated by the qualified
person specific to the floating platform mounting the crane.
Load charts should be generated based on the crane load rating
for floating service. In addition, the load charts for floating
service must comply with the specific standard it was designed
for and clearly explain the floating platform and dynamic/
environmental parameters that apply to the load chart.
The load chart should, at a minimum, identify the following:

    • Draft limits (with deck cargo considered)
    • Vessel motion limits
    • Vessel and crane list/trim limits, and
    • Vessel condition (e.g., dry bilges, watertight integrity, etc.).
    • Crane manufacturer Notes, or reference to them.
      Safe Working Load Chart with:
    • Mode of operation
    • Environmental limit
    • Capacity (net or gross)
    • Load, boom elevation, radius (with list/trim considered), and Crane configuration, such as:
    • Boom length
    • Amount of counterweight
    • Parts of wire, and
    • Block size.

Cranes and Derricks Mounted on Barges or Pontoons:
Barge- or pontoon-mounted land cranes require modified
ratings due to increased loading from list, trim, wave action,
and wind. This rating will be different for each size of pontoon
or barge used. Therefore, the load rating of barge or pontoonmounted
land cranes and derricks shall not exceed that
recommended by the manufacturer for the particular barge or
pontoon under the expected environmental conditions.
All deck surfaces of the pontoon or barge shall be above the
water. Tie-downs should be provided for derricks to transmit the
loading to the barge or pontoon. …and finally, all Cranes shall
be blocked and secured to prevent shifting.
As with any Marine Construction project, safety comes first!

2019-03-26
MCMag
Twitter Facebook linkedin Pinterest Email Print More

Authors

Posted by : MCMag
Previous Article :

NOW THIS IS SOMETHING UNIQUE!

Next Article :

INFRASTRUCTURE RESOURCE IN SOUTH FLORIDA

Related Articles

PERSONAL PROTECTION EQUIPMENT FOR WORKING OVER WATER

PERSONAL PROTECTION EQUIPMENT FOR WORKING OVER WATER

MCMag Jul 15 2020
HISTORIC YELLOWSTONE FISHING BRIDGE PROTECTED WITH SEASHIELD SERIES 500 SYSTEM

HISTORIC YELLOWSTONE FISHING BRIDGE PROTECTED WITH SEASHIELD SERIES 500 SYSTEM

MCMag Feb 26 2019
NOW THIS IS SOMETHING UNIQUE!

NOW THIS IS SOMETHING UNIQUE!

MCMag Feb 26 2019

Advertisement

Current Issue

Current Issue of Marine Construction Magazine Volume III 2022

Previous Issue

Marine Construction Magazine Vol II 2022

More Info!

Marine Construction Magazine Logo Marine Construction® Magazine publishes Six (6) Issues per year, once every 2-Months. We are by no means your typical publication. With over 30,000 readers, we pride ourselves on covering the topics of “actual usefulness” to our readers. Yes, we are a little unorthodox but…we like it like that. The bottom line is, if you are in the Marine Construction or related industry…you’ve come to the right place.

Random Posts

  • Repair of Wood and Timber Structures

    Repair of Wood and Timber Structures

    MCMag Dec 02 2021
  • ShibataFenderTeam cylindrical buoys delivered to Mildred Lake in Canada

    ShibataFenderTeam cylindrical buoys delivered to Mildred Lake in Canada

    MCMag Oct 18 2021
  • Buried Wharves Uncovered on Manhattan Waterfront

    Buried Wharves Uncovered on Manhattan Waterfront

    MCMag Jul 15 2022

Follow us

Sign up for our eNewsletter

© Copyright 2022, MarineConstruction®Magazine. All Rights Reserved