• Subscribe Today

Marine Construction® Magazine

  • Home
  • RESOURCES
    • EQUIPMENT
    • MATERIALS
    • SERVICES
    • LEGAL
    • EDUCATION
    • SAFETY
  • SUBSCRIPTION
    • PREVIOUS ISSUES
  • ADVERTISING
  • WEBINAR
  • VIDEOS
  • CONTACT
  • BLOG
  • Classifieds
  • Jobs
MCMag NEWS
  • Crowley named a Top Company for Women in Transportation   |   May 16 2025

  • John Deere Makes $100,000 Donation Match Commitment to Construction Angels Nonprofit Organization   |   May 14 2025

  • NTSB Accident Brief: The Capsizing and Sinking of the Crane Barge Ambition, Towed by Karen Koby   |   May 12 2025

  • Crane Fatigue – The Devil is in the Detailing Connection detailing is an underrated art form, especially on cranes.   |   May 09 2025

  • Selecting the Right PPE for Marine Construction   |   May 07 2025

  • ShibataFenderTeam supplies 11 Double Cone Fender Systems for Dundee Port expansion project, UK   |   May 05 2025

 
Home» BLOG»Case Study: Aarsleff constructs ferry berths in Port of Ystad, Sweden

Case Study: Aarsleff constructs ferry berths in Port of Ystad, Sweden

Mar 26 2022 BLOG Comments Off on Case Study: Aarsleff constructs ferry berths in Port of Ystad, Sweden 1270 Views

Reading Time: 3 minutes

Per Aarsleff A/S constructed two new ferry berths, FL7 and FL8, in the Port of Ystad in Sweden. The project is part of a large port expansion comprising dredging, construction of breakwaters and a new quay and pier in the outer harbor basin. The new approach area east of the pier is back-filled with dredged spoils from deepening of the port.

We installed just under 770 meters of sheet piles and drove 212 concrete piles of up to 29 meters long during the summer and autumn of 2019. We also carried out deep compaction of an area of approximately 12,000 square meters.

Ground Engineering:

New breakwater under construction in the outer harbor basin.

Prior to start-up, additional geotechnical drillings took place, and it turned out that the undrained shear strength was considerably weaker than stated in the tender documents. The altered geotechnical conditions resulted in minor changes in the project design, which were undertaken in cooperation between Aarsleff’s geotechnical specialists from the Design & Engineering department and Sweco.

Due to the hard composition of the moraine clay, a trench was excavated prior to the sheet piling work on the water to ensure that all the sheet piles could reach the desired toe level. Each sheet pile was vibro-driven with vibrators mounted on a Banut 25 and a RTG 18, respectively. Some of the sheet piles were re-driven with a S70 hydro hammer in order to achieve the desired toe level.

The quay is anchored with anchor blocks, prefabricated at our facilities in Poland, while the breakwater is braced with transverse anchors.

Alongside the quay work we drove 212 concrete piles, measuring 35×35 centimeters each, for the ramp foundations. Centrum Pæle in Sweden  supplied the piles.

The Polish ferry Wawel, shown at the Ystad quay. The ferry port provides services to Swinoujscie in Poland and forms a part of the E65 trans-European route.

After sand-filling of the quay, we carried out deep compaction using vibro wings/vibrator in the loose embedded sand – totaling approximately 7,000 spots of vibro-driving at depths of six to 10 meters. We per-formed CPT tests both before and after the deep compaction in order to control the relative density of the sand and to prove that the deep compaction had achieved the desired effect.

Aarsleff Ground Engineering is one of Europe’s leading piling contractors, and we undertake a wide variety of piling, drilling and foundation projects in Denmark and abroad. We have offices in Poland, Sweden, Germany and the UK. Our fleet covers fully hydraulic piling and drilling rigs as well as cranes and vibrators.

Data:

  • 767 linear meters of driven sheet piles AZ28-700, in lengths of 13-17 meters
  • 250 meters of quay, 40 meters wide, a local combi-wall made of AZ28 and HZ1080 (17 meters)
  • 212 concrete piles, DN 35×35 centimeters, in lengths of 22-29 meters
  • 12,000 square meters of deep compaction
  • 232 anchors installed with various technologies
  • 150 meters of a temporary quay, sheet pile in lengths of 10-12 meters

Client: Ystad Kommun & Hamn Contractor: Per Aarsleff A/S

Cooperation partners: VG Entreprenør A/S, Rhode Nielsen A/S 

Type of contract: Design and build contract, according to Swedish ABT 06

Client’s consultant: Cowi

Consulting engineer: Aarsleff Design & Engineering, Sweco DK/SE

Construction period: January 2019- October 2020

Contract value: SEK 912 millon; Ground Engineering: SEK 91 millon

SFT Parallel Motion Fenders installed at Ystad Cruise Terminal

ShibataFenderTeam supported its customer, Per Aarsleff A/S, with the installation of 16 sets of Parallel Motion Fender Systems (including steel panels of 2,200 x 4,800 mm) for berths 7 & 8 at the  Cruise Terminal in Ystad. The team from SFT’s production plant in Germany was on site for three days in August 2020 to assist during the first  installation steps.

SFT’s delivery to Ystad included two specially  designed Guide Wall Systems, each consisting

of several Element Fenders and six hinged steel panels 4,800 x 2,450 mm. Additionally, 14 sets of T-Head Bollards (75t capacity) and 20 Pillar Bollards (different capacities) were installed at the berth.

Per Aarsleff A/S handled the installation of the remaining 12 sets of Parallel Motion Fender  Systems under their own management.

2022-03-26
Facebook Twitter linkedin Pinterest Email Print More

Authors

Posted by : MCMag
Previous Article :

348 Series 2 Builds Parking Garage in Wilmington, N.C.

Next Article :

Green Bay Decking Announces New Marina Product Division

Related Articles

Crowley named a Top Company for Women in Transportation

Crowley named a Top Company for Women in Transportation

MCMag May 16 2025
John Deere Makes $100,000 Donation Match Commitment to Construction Angels Nonprofit Organization

John Deere Makes $100,000 Donation Match Commitment to Construction Angels Nonprofit Organization

MCMag May 14 2025
NTSB Accident Brief: The Capsizing and Sinking of the Crane Barge Ambition, Towed by Karen Koby

NTSB Accident Brief: The Capsizing and Sinking of the Crane Barge Ambition, Towed by Karen Koby

MCMag May 12 2025

Advertisement

Current Issue

May 2025 Issue of Marine Construction Magazine

Previous Issue

April 2025 Issue of Marine Construction Magazine
Marine Construction Magazine Logo

We cover topics of usefulness to the Marine Construction or related Industry from projects, pile driving, dock building, bridges and safety, you've found a good publication.

We are a digital publication, that goes out to over 30,000 hand-picked industry leaders and subscribers. Welcome Aboard!

Follow us

© Copyright 2022 - 2024, MarineConstruction®Magazine. All Rights Reserved
Privacy Policy | Cookie Policy | Privacy Settings | Terms of Service